Page 88 - Annual Report 2020
P. 88

1.9.3 Minerals Americas continued

                    PERU
           Chile

                                 BOLIVIA
                      Cerro
                     Colorado
               Iquique
                         Pica
          Pacific Ocean
                        CHILE
               Tocopilla
                           Calama
                         Spence
             Mejillones
                                   ARGENTINA
            Antofagasta
                           Minera Escondida
           Mine

          s1006_v1
                 Copper

          Pampa Norte (Chile)
          Overview                                           Looking ahead
          Pampa Norte consists of two wholly owned assets in the Atacama   Production for FY2021 is expected to be between 240 and 270 kt,
          Desert in northern Chile – Spence and Cerro Colorado. Spence and   reflecting the reduced operational workforce due to COVID-19, the
          Cerro Colorado produce high-quality copper cathodes through   start-up of the SGO project and expected grade decline of
          leaching, solvent extraction and electrowinning processes.  approximately 7 per cent.
          Key developments during FY2020                     SGO will produce first copper between December 2020 and
          Pampa Norte copper production for FY2020 decreased by   March 2021 and plans are on track to redesign the approach
          2 per cent to 243 kt, mainly due to a 14 per cent decline in stacked   to operations at Spence to optimally balance the requirements
          ore grade.                                         of the concentrate and cathodes processes. The first batch
                                                             of the ultra-class truck fleet arrived at Spence in FY2020 and
          The Spence Growth Option (SGO) to construct a 95 ktpd ore   the remaining units are expected to arrive in the next two years.
          concentrator and the outsourcing of a 1,000 litre per second   The BHP Operating System deployment at Spence started in
          desalination plant is 93 per cent complete. As a result of measures   January 2020 and is expected to continue during FY2021. Similar to
          put in place to reduce the spread of COVID-19, first production    Escondida, Spence will be undertaking studies on various material
          is now expected between December 2020 and March 2021. The   handling technologies, such as automated trucks, trolley assistance
          commissioning of the desalination plant and capitalisation of the   and in-pit crushers and conveyors to increase mine productivity
          associated US$600 million lease (approximate) will now occur    and improve cost competitiveness.
          in the first half of FY2021.
                                                             On 1 July 2020, Cerro Colorado announced it had started a
               For more information about SGO,               four-month process to adjust its mine plan to reduce throughput
               refer to section 6.5.                         and costs to achieve improved cash returns and ensure viable
                                                             mining operations for the remaining period of its current
                                                             environmental licence, which expires at the end of CY2023.