6.5 Major projects

          At the end of FY2020, BHP had six major projects under development in petroleum, copper, iron ore and potash, with a combined budget
          of US$11.4 billion over the life of the projects.
          Capital and exploration expenditure of US$7.6 billion in FY2020 was within guidance. Capital and exploration expenditure of approximately
          US$7 billion is now expected for FY2021 and is approximately US$1 billion lower than previous guidance predominantly due to the deferral
          of a number of our petroleum projects in order to maximise value. This guidance includes a US$0.7 billion exploration program in FY2021,
          with approximately US$450 million for petroleum exploration and appraisal expenditure.
          Projects in execution at the end of FY2020
                                                                          Date of initial production  Capital expenditure (US$M)  (1)
          Commodity   Project and ownership    Capacity  (1)                         Target             Budget
          Projects under development
          Petroleum   Atlantis Phase 3         New subsea production system that will   CY2020            696
                      (US Gulf of Mexico)      tie back to the existing Atlantis facility,
                      44% (non-operator)       with capacity to produce up to 38,000
                                               gross barrels of oil equivalent per day.
                                               On schedule and on budget. First
                                               production achieved in July 2020.
                                               Overall project is 79% complete
          Petroleum   Ruby                     Five production wells tied back into   CY2021              283
                      (Trinidad and Tobago)    existing operated processing facilities,
                      68.46% (operator)        with capacity to produce up to 16,000
                                               gross barrels of oil per day and
                                               80 million gross standard cubic feet of
                                               natural gas per day. On schedule and on
                                               budget. Overall project is 28% complete
          Petroleum   Mad Dog Phase 2          New floating production facility with    CY2022           2,154
                      (US Gulf of Mexico)      the capacity to produce up to 140,000
                      23.9% (non-operator)     gross barrels of crude oil per day.
                                               On schedule and on budget. Overall
                                               project is 77% complete
          Iron Ore    South Flank (Australia)  Sustaining iron ore mine to replace    CY2021             3,061
                      85% (operator)           production from the 80 Mtpa Yandi
                                               Mine. Overall project is 76% complete
          Copper      Spence Growth Option     New 95 ktpd concentrator is expected   FY2021             2,460
                      (Chile)                  to incrementally increase Spence’s
                                               payable copper in concentrate
                                               production by approximately 185 ktpa
                                               in the first 10 years of operation and
                                               extend the mining operations by more
                                               than 50 years. Overall project
                                               is 93% complete. Project approved
                                               on 17 August 2017
                                                                                                         8,654


          Other projects in progress at the end of FY2020
                                                                                            Capital expenditure (US$M)  (1)
          Commodity   Project and ownership    Scope                                                    Budget
          Projects under development
          Potash      Jansen Potash Project    Investment to finish the excavation and lining of the production   2,700
                      (Canada) 100%            and service shafts, and continue the installation of essential
                                               surface infrastructure and utilities
                                                                                                         2,700
          (1)  Unless noted otherwise, references to capacity are on a 100 per cent basis, references to capital expenditure from subsidiaries are reported on a 100 per cent basis
           and references to capital expenditure from joint operations reflect BHP’s share.